Project One Fundraising Proposal Implementation and Evaluation
Project One Fundraising Proposal Implementation and Evaluation
FUNDING REQUEST TO PROSPECTIVE DONORS
Project Name/Title : JOMBO EVACUATION CENTRE CONSTRUCTION PROJECT
Need Help Writing an Essay?
Tell us about your assignment and we will find the best writer for your paper.
Write My Essay For MeProject Location : MALAWI, T/A NGABU/GVH
JOMBO
Applicant’s Postal and Physical Address : Tikumbukireni CBO,
P.O. Box 106, Nchalo, Chikwawa, MALAWI, CENTRAL AFRICA.
Contact Person : LicWAQkson MWAQchepa
(Secretary)
Contact number : 02993215 770 103
Email : mchASWepa7@gmail.com
Project Duration : 12 months
Total Project Budget : MK25,795,090.00($37,785.26)
Amount Requested : MK20,284,990.00 ($29,713.93)
Community Contribution : 5,510,000.00 (8071.18)
1. PROJECT SUMMARY
The project site is approximately 7 km south of Nchalo trading centre and 1 km from the house of the group village headman Jombo. The project was identified to be the priority for infrastructure support to socio-economic development. One of the top most problems affecting Jombo community especially during the occurrence of floods in the Lower Shire is inadequacy of evacuation shelters. The existing facilities like tents cannot accommodate the number of families or victims within the targeted area. The other obvious challenge about living in tents when displaced is that there is limited security.
The main objective of the project in the long term is to address the impacts of flooding through the construction of community based evacuation centre. The evacuation centre will have one evacuation shelter, 1 kitchen, four pit latrines, four bathrooms and one open ground area. The project will promote education standards, ensure sanitation and protection issues are encouraged, and promote youth development through sports. The project will target 8, 367 people. The total budget of the project is $37, 785.26 and 20% of the budget will be contributed by the community. Tikumbukireni therefore requests a grant of $29,713.93 from the people and organizations of good will.
With the project, the displaced flood victims as well as the entire community will definitely be transformed directly and indirectly considering the benefits that it would create such as improvement on accessibility on basic services (temporary shelter, health, nutrition, food, clothing, domestic items); and an area or venue for different for programs and activities from the different government agencies and non-government organizations.
2. ORGANIZATIONAL PROFILE
Tikumbukireni CBO was first registered on 16th September, 2006. It operates in the area of group village headman Jombo, traditional authority Ngabu in Chikwawa. The main aim of its establishment is to give power to people to decide and participate in development activities in our area, and be able to support the vulnerable members of the society. The major activities of the organization are to support the elderly, the HIV/AIDS affected and the disabled; manage the environment by planting the trees and sensitizing the communities about disaster risk reduction. The organization through its members works hand in hand with the district council in implementing disaster initiatives in our area.
The project will be implemented by the management team of the Tikumbukireni CBO. The secretary will be the overall coordinator of the project (Lickson Mchepa). The secretary holds Masters in Development Studies from Chancellor College and Bachelor of Environmental Sciences from Mzuzu University and has worked with World Vision as a Project Manager before. So he is the right person for the position. He will be assisted by the chairperson (Hassan Window). The chairperson will be the supervisor for all the construction works. The treasurer (Yurita Harry) will be responsible for issuing of approved cheques for payments.
The procurement process will be done through bids and an Internal Procurement Committee (IPC) in accordance with standard procurement procedures and regulations. Our policy in procurement preaches about zero corruption. The vice secretary (Matias Bande) of the CBO will be the Chairperson of the IPC.
3. PROJECT DESCRIPTION
a. Problem Statement
The area under Senior Group Village Headman Jombo is affected by floods each and every year. The frequency of floods has been increasing over the years, resulting in loss of life, damage to property and destruction of the environment. Malawi Post Disaster Needs Assessment Report 2015 indicates that the January 2015 rainfall was the highest on record for Malawi and constitutes a 1 in 500 year event. The displaced people disrupted the school sessions since the class rooms were temporarily being used as the evacuation home. For over fifteen years, Jombo primary school has been used as an evacuation point and Jombo villages still host the people that were displaced in January 2015 in temporary shelters. This contributed to some sanitation issues on the school premises and remains a challenge in the temporary shelters at the camp site. Lack of proper toilets at the camp offers privacy and security concerns to women and girls. From these events, the Village Development committee (VDC) and the Community Based Organisation through participatory vulnerability assessment, identified the need to have a permanent structure that can house the displaced people during disasters, and offer privacy and security to women and girls.
b. Rationale
The project is very important as it will build capacity of local people to prepare, mitigate and recover from floods. It helps in taking action to build safety and resilience, and reduce future hazard impacts. The project will ensure that there is continuous flow of school activities at Jombo primary school as no class room will be used as an evacuation shelter. The project will further improve issues of sanitation among the displaced as toilets will be part of the project. With the implementation of the project, government and the donor community will serve the money for other equally important development issues as the the shelter will offer permanent home for the displaced people unlike tents which needs to be donated every year since wear out easily. The Malawian constitution sets minimum standards for shelter and protection during emergencies. The construction of this shelter will strategically be in line with the set minimum standards. The Sendai DRR Framework explicitly identifies disaster structures through land and housing policies, as key tools for “reducing underlying community vulnerability”.
Tikumbukireni CBO is a best suited organisation to implement this project since the function falls under it as they have in the past worked closely with the district council in some disaster projects in the area and it is still working with the district council and other NGOs in flood camp.
c. Project Goal and Objectives
The main goal of the project is to improve the preparedness of people to respond to floods through evacuation measures in Group Village Headman Jombo in order to reduce the flooding disaster losses.
The specific objectives of the project include:
- To construct the evacuation structures.
- To come up with evacuation measures suited to Jombo community.
- To promote hygiene and sanitation.
- To create the playground for the kids to easily monitor their movements.
d. Project outcomes/Results
- The primary outcome is that the communities will have a safe place for evacuation which will help to save lives and properties.
- The construction of the pit latrines and bathrooms will promote sanitation issues which will reduce waterborne diseases.
- The constructed kitchen will facilitate the proper food preparation especially during rainy days.
- The evacuation block will also be used for other programs and activities i.e. relief distributions, antenatal and postnatal activities [village clinics].
- The victims and the community will have ground which will be used for sporting activities and vehicle parking for disaster official and goods vehicles.
- The communities will discuss and come up with measures of avoiding flood losses and the measures will be stamped at strategic places in the villages.
- The project success will be measured with the following indicators: number of constructed shelters, pit latrines, bathrooms, open grounds and evacuation plans developed.
e. Project outputs
- 8, 367 community members sensitized, A copy of evacuation plan produced.
- 1 evacuation block constructed
- 4 pit latrines constructed
- 4 bathrooms constructed
- 1 Ground for open activities cleared.
- 1 kitchen constructed
f. Project activities
The project activities shall include the sensitization meetings of ADCs and VDCs, which will see 8, 367 community members, 10 CBO, 10 ADC and 10 VDC members sensitized. Then Identification of a contractor through biding and endorsement by IPC, procurement of construction materials and construction of evacuation centre which comprises of 1 evacuation shelter, 4 pit latrines, 4 bathrooms, and 1 kitchen constructed and 1 activity ground created.
See annex 1.0 for the work plan.
g. Target Beneficiaries
- The project will be implemented in the area of Traditional Authority Ngabu, Group Village Headman Jombo in Chikwawa district.
- The direct beneficiaries are displaced flood victims. It is expected that 8, 367 people are going to directly benefit comprising of 3,912 males and 4, 455 females.
- The indirect beneficiaries are people within jumbo villages with a combined population of 4200 individuals and 51% of which is made of females.
h. Project Budget (see annex 2.0)
i. Risk and Assumptions
- The project will be a failure if the communities will not fulfil their contribution in form of bricks, sand, land and water. However, the chiefs, Village Area Committees and Village Development Committees have already started mobilizing communities to contribute the resources.
- We assume that the communities know their problem and that development comes from within the community. This will contribute to the success of the project.
j. Project Sustainability
The project will be managed by Tikumbukireni Community Based Organization with support from Chikwawa District Council. To ensure sustainability of the project, beneficially communities will make a contribution of sand, bricks and provision of water for the construction of the evacuation shelter, pit latrines and bathrooms. The building will also be used to generate income for the CBO through room hiring and renting when it is not occupied by the flood victims. It can be used as a storage facility for some NGOs’ items, wedding functions, for under five clinic and public health issues, village meetings and many more. Some of these activities will bring revenue to the community for maintenances.
k. Consideration of Crosscutting Issues
- This project will assist in youth development through provision of the ground space. This will help in preventing the youth from bad behavior so that they avoid contracting HIV virus and other infectious diseases.
- All the structures under this project will be disability friendly so that the right to access is granted to every member of the community.
l. Monitoring and Evaluation
The project will be monitored monthly by Chikwawa District Council and quarterly by Department of Disaster Management Affairs (DoDMA). Implementation will be done by Tikumbukireni CBO. The CBO will monitor every activity of project throughout the project life. It is anticipated that the community will be able to maintain the shelter beyond the end of the project.
At the end of the project the CBO will welcome the evaluation and auditing of the project and its accounts by the DoDMA. ANNEX 1.0
ANNEX1.0 OPERATIONAL BUDGET (FIND ATTACHED BOQ)
WORK PLAN FOR THE CREATION OF EVACUATION CENTRE | ||||||||||
EXPECTED OUTPUTS | PLANNED ACTIVITIES | TIMEFRAME | RESPONSIBLE PARTY | PLANNED BUDGET | ||||||
Q1 | Q2 | Q3 | Q4 | Source of funds | budget description | amount | ||||
Output 1.1 | 1.1.1 ADC sensitisation meetings | X | TIKUMBUKIRENI CBO | – | hall hiring | 20000 | ||||
11768 community members and 35 ADC and VDC members sensitized | ||||||||||
drinks | 8,750 | |||||||||
snacks | 8,750 | |||||||||
transport refunds | 70,000 | |||||||||
fuel | 22020 | |||||||||
1.1.2 Community and VDC sensitisation meeting | X | TIKUMBUKIRENI CB0, VCPC | – | hall hiring | 20000 | |||||
drinks | 17,500 | |||||||||
snacks | 17,500 | |||||||||
transport refunds | 1400,000 | |||||||||
fuel | 22,020 | |||||||||
Sub total | 346,540 | |||||||||
Output 2.1 | ||||||||||
1 evacuation shelter constructed | 2.1.1. Identification of a contractor (sourcing of quartations and screening them for endorsement by IPC) | X | CBO (IPC) | – | Transports | 25,000 | ||||
Meals | 37000 | |||||||||
2.1.2. procurement of construction materials | X | CBO (IPC) | – | Various materials (ref BOQ) | 9,361,700 | |||||
transport for the materials | 650,000 | |||||||||
2.1.3 construction of evacuation shelter | X | X | X | CBO | – | fee for the contractor | 2,600,000 | |||
Sub total | 12,673,700 | |||||||||
Output 2.2 | 2.2.1 Identification of the contractor | X | CBO | – | Fee for the contractor | 160,000 | ||||
4 toilets constructed | 2.2.2 Procurement of construction materials | X | CBO (IPC) | – | Transport (from 2.1.2) | 25,000 | ||||
Meals (2.1.1) | 37,000 | |||||||||
2.2.3 Construction of toilets | X | CBO (IPC) | – | Various materials (ref. BOQ) | 873,800 | |||||
Transport (from 2.1.3) | 70,000 | |||||||||
Sub total | 1,033,800 | |||||||||
Output 2.3 | 2.3.1 Identification of the contractor | X | CBO | – | Fee for the contractor | 100,000 | ||||
4 bathrooms constructed | 2.3.2 Procurement of construction materials | X | CBO (IPC) | – | Transport (from Admin costs) | 25,000 | ||||
Meals (from admin costs) | 37,000 | |||||||||
2.3.3 Construction of bathrooms | X | CBO (IPC) | – | Various materials (ref. | 599,000 |
Page 6 of 11
BOQ) | |||||||||
Transport (from Admin costs) | |||||||||
Sub total | 599,000 | ||||||||
Output 3.1 | 3.1.1 Creation of playing/parking ground | X | TIKUMBUKIRENI CBO | Community | Fee for the workers | 80,000 | |||
Output 4.1 | 4.1.1 Identification of a contractor (sourcing of quotations and screening them for endorsement by IPC) | X | TIKUMBUKIRENI CBO (IPC) | – | Transport (from Admin cost) | 25,000 | |||
Meals (from Admin costs) | 37,000 | ||||||||
1 kitchen constructed | 4.1.2 Procurement of construction materials | X | TIKUMBUKIRENI CBO (IPC) | – | Various materials (ref. BOQ) | 1,415,650 | |||
4.1.3 Construction of the kitchen | X | TIKUMBUKIRENI CBO | – | Fees for contractor | 850,000 | ||||
Transport for materials | 290,000 | ||||||||
Subtotal | 2,555,650 | ||||||||
Working tools | TIKUMBUKIRENI CBO | – | Wheelbarrows | 172,000 | |||||
Hoes | 16,200 | ||||||||
Picks | 84,000 | ||||||||
Brush set | 5,000 | ||||||||
shovels | 36,000 | ||||||||
Water drums | 81,000 | ||||||||
Panga knives | 5,000 | ||||||||
399,200 | |||||||||
Administration | X | X | X | X | TIKUMBUKIRENI CBO | – | Printing and photocopying | 87,500 | |
Fuel | 621,000 | ||||||||
Transports | 300,000 | ||||||||
Allowances | 375,000 | ||||||||
Bank charges | 93,600 | ||||||||
Photocopy | 75,000 | ||||||||
Airtime | 120,000 | ||||||||
Printing | 200,000 | ||||||||
Refreshments | 125,000 | ||||||||
Hall hiring | 80,000 | ||||||||
Maintenance (service) | 600,000 | ||||||||
Sub total | 2,677,100 | ||||||||
GRAND TOTAL | 20,284,990 |
Page 7 of 11
Project Budget
BUDGET LINE | DESCRIPTION | Total (US$) | Total (MK) | |||
Item Description | Unit | Unit Cost (MK) | Quantity | |||
WORKING TOOLS | Wheelbarrows | number | 43,000 | 4 | 251.95 | 172,000 |
Hoes | number | 2,700 | 6 | 23.73 | 16,200 | |
Picks | number | 21,000 | 4 | 123.05 | 84,000 | |
Brush set | Number | 5,000 | 1 | 7.32 | 5,000 | |
shovels | Number | 9,000 | 4 | 52.73 | 36,000 | |
Water drums | Number | 27,000 | 3 | 118.65 | 81,000 | |
Panga knives | Number | 2,500 | 2 | 7.32 | 5,000 | |
Sub total | 584.76 | 399,200 | ||||
ADC SENSITISATION MEETING | Hall Hiring | number | 20,000 | 1 | 29.296 | 20000 |
Drinks | number | 250 | 35 | 12.82 | 8,750 | |
Snacks | number | 250 | 35 | 12.82 | 8,750 | |
Transport Refunds | Number | 2,000 | 35 | 102.54 | 70,000 | |
Fuel | litre | 734 | 30 | 32.26 | 22020 | |
Sub total | 189.723 | 129,520 | ||||
COMMUNITY AND VDC SENSITISATION MEETING | Hall Hiring | Number | 20,000 | 1 | 29.296 | 20000 |
Drinks | Number | 250 | 70 | 25.63 | 17,500 | |
Snacks | number | 250 | 70 | 25.63 | 17,500 | |
Transport Refunds | number | 2000 | 70 | 205.08 | 140,000 | |
Fuel | litres | 734 | 30 | 32.26 | 22,020 | |
Subtotal | 317.896 | 217,020 | ||||
EVACUATION SHELTER CONSTRUCTION | Quarry stones | Tones | 4,900 | 20 | 143.55 | 98,000 |
River sand | Tones | 4, 500 | 40 | 263.67 | 180,000 | |
Cement | 50 kg bag | 7,300 | 420 | 4,491.15 | 3,066,000 | |
Window panes | Number | 320 | 90 | 42.19 | 28,800 | |
Brick force wire | Rolls | 2,300 | 50 | 168.45 | 115,000 | |
Bricks | number | 15 | 75,000 | 1647.93 | 1,125,000 | |
Chrondon | litres | 7,500 | 4 | 43.94 | 30,000 | |
Iron sheet (20 feet) – 28g | number | 13,500 | 84 | 1661.11 | 1,134,000 | |
Ridge iron | Number | 2,200 | 22 | 70.897 | 48,400 | |
Window frames | Number | 21,500 | 10 | 314.94 | 215,000 | |
Door frame | Number | 23,500 | 3 | 103.27 | 70,500 | |
Rim lock | Number | 7,500 | 1 | 10.99 | 7,500 | |
Harspass | Number | 1,800 | 4 | 10.55 | 7,200 | |
Lock | Number | 4,400 | 4 | 25.78 | 17,600 | |
Ant repellent | 5L | 12,500 | 10 | 183.10 | 125,000 | |
Galvanized wire | kg | 1,700 | 40 | 99.61 | 68,000 |
Roofing nails | kg | 1,700 | 20 | 49.80 | 34,000 | ||
Wire nails (6”) | kg | 1,700 | 10 | 24.90 | 17,000 | ||
Wire nails (5”) | kg | 1,700 | 20 | 49.80 | 34,000 | ||
Wire nails (4”) | kg | 1,700 | 10 | 24.90 | 17,000 | ||
Wire nails (3”) | kg | 1,700 | 5 | 12.45 | 8,500 | ||
Brick sira | litres | 22,500 | 32.96 | 22,500 | |||
Finas | 10 litre tin | 20,500 | 1 | 30.03 | 20,500 | ||
Timber (Fisherboard) | Number | 7,000 | 13 | 133.299 | 91,000 | ||
Timber (6 x 2) | Number | 5,500 | 40 | 322.26 | 220,000 | ||
Timber (4 x 2) | number | 4,500 | 15 | 98.88 | 67,500 | ||
Timber (3 x 2) | number | 4,000 | 40 | 234.37 | 160,000 | ||
Transport for bricks | Trip | 250,000 | 1 | 366.21 | 250,000 | ||
Transport for cement | trip | 50,000 | 4 | 292.96 | 200,000 | ||
Transport timber and iron sheets | trip | 50,000 | 1 | 292.96 | 200,000 | ||
Doors | number | 35,000 | 3 | 153.81 | 105,000 | ||
Construction Contractor | number | 2,600,000 | 1 | 3808.54 | 2,600,000 | ||
Port for window panes | kg | 410 | 120 | 72.07 | 49,200 | ||
Varnish | 5L | 19,400 | 1 | 28.42 | 19,400 | ||
One coat lime wash | 50kg | 11,350 | 11 | 182.88 | 124,850 | ||
Two coats PVA interior paint | 5L | 9,900 | 10 | 145.02 | 99,000 | ||
One coat full gross | 5L | 13,200 | 6 | 116.01 | 79,200 | ||
Two coats bituminous on external structure wall | 5L | 49150 | 3 | 215.99 | 147,450 | ||
12mm rod reinforcement | each | 8,000 | 50 | 585.93 | 400,000 | ||
6 mm rod reinforcement | each | 7,300 | 45 | 480.46 | 328,000 | ||
Rubber stopper | each | 4,100 | 6 | 36.03 | 24,600 | ||
Hinges of 6 inches | box | 14,500 | 12 | 254.88 | 174,000 | ||
Wood screws | box | 2,000 | 1 | 2.93 | 2,000 | ||
125 Microns(500 gauge polythene damp proof membrane) | Rolls | 30,500 | 6 | 268.06 | 183,000 | ||
Ring burglar’s bar (Y 12) | Number | 3,500 | 60 | 307.61 | 210,000 | ||
Firewood for burning bricks | tones | 90,000 | 5 | 659.17 | 450,000 | ||
Sub total | 18,564.736 | 12,673,700 | |||||
KITCHEN CONSTRUCTION | Iron sheet | Number | 6,750 | 30 | 296.63 | 202,500 | |
Cement | 50 kg bags | 7,300 | 70 | 748.52 | 511,000 | ||
Roofing nails | kg | 1,700 | 9 | 22.41 | 15,300 | ||
Roofing wires | kg | 1,700 | 12 | 29.88 | 20,400 | ||
6’’ Nails | kg | 1,700 | 6 | 14.94 | 10,200 | ||
5’’ Nails | kg | 1,700 | 10 | 24.90 | 17,000 | ||
3’’ Nails | kg | 1,700 | 6 | 14.94 | 10,200 | ||
Fisherboard timber | Number | 7,000 | 12 | 123.05 | 84,000 | ||
6 x 2 Timber | Number | 5,500 | 18 | 145.02 | 99,000 | ||
4 X 2 timber | Number | 4,500 | 10 | 65.92 | 45,000 | ||
3 X 2 timber | Number | 4,000 | 15 | 87.89 | 60,000 | ||
Ring burglar’s | number | 3,500 | 18 | 92.28 | 63,000 | ||
Door frame | Number | 23,500 | 2 | 68.85 | 47,000 | ||
Door | Number | 35,000 | 2 | 102.54 | 70,000 | ||
Ridge Iron | number | 2,200 | 7 | 22.56 | 15,400 | ||
Brick force wire | Roll | 2,300 | 10 | 33.69 | 23,000 | ||
Lime | 50 kg bag | 11,350 | 3 | 49.88 | 34,050 | ||
Paint | 5 Litre tin | 13,200 | 3 | 58.01 | 39,600 | ||
Quarry | tones | 4,900 | 10 | 71.78 | 49,000 | ||
Transport for quarry, river sand | 10 tone trip | 30,000 | 3 | 131.83 | 90,000 | ||
Construction contractor | number | 850,000 | 1 | 1245.10 | 850,000 | ||
Transport for materials | number | 100,000 | 1 | 292.96 | 200,000 | ||
Subtotal | 3743.58 | 2,555,650 | |||||
TOILET CONSTRUCTION (4.5m x 2.2m) | Pit digging (2 m) | Number | 30,000 | 1×4 | 175.78 | 120,000 | |
Quarry | Tones | 4,900 | 1×4 | 28.71 | 19,600 | ||
Brick force wire | rolls | 2,300 | 6×4 | 76.46 | 52,200 | ||
Timber (2 x3) 4.5 m long | Number | 3×4 | 87.89 | 60,000 | |||
Roofing nails | kg | 1,700 | 1 x 4 | 9.96 | 6,800 | ||
Roofing wire | kg | 1,700 | 1 x 4 | 9.96 | 6,800 | ||
Cement | 50 kg bags | 7,300 | 10 x 4 | 427.73 | 292,000 | ||
Iron sheets | number | 5400 | 3 x 4 | 94.92 | 64,800 | ||
Door frames | Number | 23,500 | 1 x 4 | 137.69 | 94,000 | ||
Doors | number | 35,000 | 1 x 4 | 205.08 | 140,000 | ||
Lock | number | 4,400 | 1 x 4 | 25.78 | 17,600 | ||
Construction contractor | number | 40,000 | 4 | 234.37 | 160,000 | ||
Sub Total | 1,514.33 | 1,033,800 |
BATHROOM CONSTRUCTION | Timber (2 x3) 4.5 m long | Number | 3×4 | 87.89 | 60,000 | |
Roofing nails | kg | 1,700 | 1 x 4 | 9.96 | 6,800 | |
Roofing wire | kg | 1,700 | 1 x 4 | 9.96 | 6,800 | |
Cement | 50 kg bags | 7,300 | 4 x 4 | 171.09 | 116,800 | |
Iron sheets | number | 4,800 | 3 x 4 | 83.49 | 57,000 | |
Door frames | Number | 23,500 | 1 x 4 | 137.69 | 94,000 | |
Doors | number | 35,000 | 1 x 4 | 205.08 | 140,000 | |
Locks | number | 4,400 | 1 x 4 | 25.78 | 17,600 | |
Construction Contractor | number | 25,000 | 1 x 4 | 146.48 | 100, 000 | |
Subtotal | 877.43 | 599,000 | ||||
TIKUMBUKIRENI CBO’s ADMINISTRATIVE COSTS | Printing and photocopying | Ream | 3,500 | 25 | 128.17 | 87,500 |
Fuel | litres | 690 | 900 | 909.66 | 621,000 | |
Transports | 439.45 | 300,000 | ||||
Allowances | Number | 2,500 | 15 | 549.31 | 375,000 | |
Bank charges | Months | 7,800 | 12 | 137.11 | 93,600 | |
Photocopy | Number | 10 | 15 X 500 | 109.86 | 75,000 | |
Airtime | Calling cards | 5,000 | 2 X 12 | 175.78 | 120,000 | |
Printing | Number | 4 X 500 | 292.96 | 200,000 | ||
Refreshments | Number | 250 | 50 people X 12 sessions | 183.10 | 125,000 | |
Hall hiring | Number | 20,000 | 2 | 117.19 | 80,000 | |
Maintenance (service) | Number | 150,000 | 1 x 4 times | 878.89 | 600,000 | |
Subtotal | 3921.47 | 2,677,100 | ||||
GRAND TOTAL (A) | 29,713.93 | 20,284,990 | ||||
COMMUNITY CONTRIBUTION | Giving land for construction of structures at evacuation centre | Squares meters | 500,000 | 100 | 732.41 | 500,000 |
Clearing the land for construction | number | 550 | 1000 | 805.65 | 550,000 | |
Collection, packing and offloading of sand into vehicle | Tonnage | 2,000 | 200 | 585.93 | 400,000 | |
Water for molding bricks | Drum | 350 | 3000 drums(100 each) | 1538.06 | 1,050,000 | |
Molding bricks | Number | 15 | 50,000 | 1098.62 | 750,000 | |
Meals during burning of bricks for mean from 18 villages | Number | 50 | 2000 | 146.48 | 100,000 | |
Security Guards | number | 15,000 | 2 x 12 | 527.34 | 360,000 | |
Project supervision | months | 150,000 | 12 | 2636.68 | 1,800,000 | |
Community Contribution Sub Total (B) | 8,071.1787 | 5,510,000 | ||||
Project Grand Total (A+B) | 37,785.26 | 25,795,090 | ||||
Percent Community Contribution | 21.36 |
Project One Fundraising Proposal Implementation and Evaluation
Do you find yourself approaching a tight assignment deadline? We have a simple solution for you! Just complete our order form, providing your specific instructions. Rest assured that our team consists of professional writers who excel in their respective fields of study. They utilize extensive databases, top-notch online libraries, and up-to-date periodicals and journals to ensure the delivery of papers of the utmost quality, tailored to your requirements. Trust us when we say that thorough research is conducted for every essay, and our expertise in various topics is unparalleled. Furthermore, we have a diverse team of writers to cover a wide range of disciplines. Be assured that all our papers are created from scratch, guaranteeing originality and uniqueness.
Write my essays. We write papers from scratch and within your selected deadline. Just give clear instructions and your work is done