FUNDING REQUEST TO PROSPECTIVE DONORS

Project Name/Title    :  JOMBO EVACUATION CENTRE  CONSTRUCTION PROJECT

Need Help Writing an Essay?

Tell us about your assignment and we will find the best writer for your paper.

Write My Essay For Me

Project Location                                    :                 MALAWI, T/A  NGABU/GVH

JOMBO

Applicant’s Postal and Physical Address :                    Tikumbukireni CBO,

P.O. Box 106, Nchalo, Chikwawa, MALAWI, CENTRAL AFRICA.

Contact Person                                      :                  LicWAQkson MWAQchepa 

(Secretary)

Contact number                                    :                  02993215 770 103

Email                                                    :                   mchASWepa7@gmail.com

Project Duration                                    :                  12 months

Total Project Budget                              :                  MK25,795,090.00($37,785.26)

Amount Requested                                :                  MK20,284,990.00 ($29,713.93)

Community Contribution                        :                  5,510,000.00 (8071.18)

1. PROJECT SUMMARY 

The project site is approximately 7 km south of Nchalo trading centre and 1 km from the house of the group village headman Jombo. The project was identified to be the priority for infrastructure support to socio-economic development. One of the top most problems affecting Jombo community especially during the occurrence of floods in the Lower Shire is inadequacy of evacuation shelters. The existing facilities like tents cannot accommodate the number of families or victims within the targeted area. The other obvious challenge about living in tents when displaced is that there is limited security. 

The main objective of the project in the long term is to address the impacts of flooding through the construction of community based evacuation centre. The evacuation centre will have one evacuation shelter, 1 kitchen, four pit latrines, four bathrooms and one open ground area. The project will promote education standards, ensure sanitation and protection issues are encouraged, and promote youth development through sports. The project will target 8, 367 people. The total budget of the project is $37, 785.26 and 20% of the budget will be contributed by the community. Tikumbukireni therefore requests a grant of $29,713.93 from the people and organizations of good will.

With the project, the displaced flood victims as well as the entire community will definitely be transformed directly and indirectly considering the benefits that it would create such as improvement on accessibility on basic services (temporary shelter, health, nutrition, food, clothing, domestic items); and an area or venue for different for programs and activities from the different government agencies and non-government organizations.  

2. ORGANIZATIONAL PROFILE

Tikumbukireni CBO was first registered on 16th September, 2006. It operates in the area of group village headman Jombo, traditional authority Ngabu in Chikwawa. The main aim of its establishment is to give power to people to decide and participate in development activities in our area, and be able to support the vulnerable members of the society. The major activities of the organization are to support the elderly, the HIV/AIDS affected and the disabled; manage the environment by planting the trees and sensitizing the communities about disaster risk reduction. The organization through its members works hand in hand with the district council in implementing disaster initiatives in our area. 

The project will be implemented by the management team of the Tikumbukireni CBO. The secretary will be the overall coordinator of the project (Lickson Mchepa). The secretary holds Masters in Development Studies from Chancellor College and Bachelor of Environmental Sciences from Mzuzu University and has worked with World Vision as a Project Manager before. So he is the right person for the position. He will be assisted by the chairperson (Hassan Window). The chairperson will be the supervisor for all the construction works. The treasurer (Yurita Harry) will be responsible for issuing of approved cheques for payments.

The procurement process will be done through bids and an Internal Procurement Committee (IPC) in accordance with standard procurement procedures and regulations. Our policy in procurement preaches about zero corruption. The vice secretary (Matias Bande) of the CBO will be the Chairperson of the IPC.

3. PROJECT DESCRIPTION 

a. Problem Statement 

The area under Senior Group Village Headman Jombo is affected by floods each and every year. The frequency of floods has been increasing over the years, resulting in loss of life, damage to property and destruction of the environment. Malawi Post Disaster Needs Assessment Report 2015 indicates that the January 2015 rainfall was the highest on record for Malawi and constitutes a 1 in 500 year event. The displaced people disrupted the school sessions since the class rooms were temporarily being used as the evacuation home. For over fifteen years, Jombo primary school has been used as an evacuation point and Jombo villages still host the people that were displaced in January 2015 in temporary shelters. This contributed to some sanitation issues on the school premises and remains a challenge in the temporary shelters at the camp site. Lack of proper toilets at the camp offers privacy and security concerns to women and girls. From these events, the Village Development committee (VDC) and the Community Based Organisation through participatory vulnerability assessment, identified the need to have a permanent structure that can house the displaced people during disasters, and offer privacy and security to women and girls.

b. Rationale

The project is very important as it will build capacity of local people to prepare, mitigate and recover from floods. It helps in taking action to build safety and resilience, and reduce future hazard impacts. The project will ensure that there is continuous flow of school activities at Jombo primary school as no class room will be used as an evacuation shelter. The project will further improve issues of sanitation among the displaced as toilets will be part of the project. With the implementation of the project, government and the donor community will serve the money for other equally important development issues as the the shelter will offer permanent home for the displaced people unlike tents which needs to be donated every year since wear out easily. The Malawian constitution sets minimum standards for shelter and protection during emergencies. The construction of this shelter will strategically be in line with the set minimum standards. The Sendai DRR Framework explicitly identifies disaster structures through land and housing policies, as key tools for “reducing underlying community vulnerability”. 

Tikumbukireni CBO is a best suited organisation to implement this project since the function falls under it as they have in the past worked closely with the district council in some disaster projects in the area and it is still working with the district council and other NGOs in flood camp.

c. Project Goal and Objectives

The main goal of the project is to improve the preparedness of people to respond to floods through evacuation measures in Group Village Headman Jombo in order to reduce the flooding disaster losses.

The specific objectives of the project include:

  1. To construct the evacuation structures. 
  2. To come up with evacuation measures suited to Jombo community.
  3. To promote hygiene and sanitation.
  4. To create the playground for the kids to easily monitor their movements.

d. Project outcomes/Results

  • The primary outcome is that the communities will have a safe place for evacuation which will help to save lives and properties.
  • The construction of the pit latrines and bathrooms will promote sanitation issues which will reduce waterborne diseases. 
  • The constructed kitchen will facilitate the proper food preparation especially during rainy days.
  • The evacuation block will also be used for other programs and activities i.e. relief distributions, antenatal and postnatal activities [village clinics].
  • The victims and the community will have ground which will be used for sporting activities and vehicle parking for disaster official and goods vehicles. 
  • The communities will discuss and come up with measures of avoiding flood losses and the measures will be stamped at strategic places in the villages.
  • The project success will be measured with the following indicators: number of constructed shelters, pit latrines, bathrooms, open grounds and evacuation plans developed.

e. Project outputs

  • 8, 367 community members sensitized,   A copy of evacuation plan produced.
  • 1 evacuation block constructed
  • 4 pit latrines constructed
  • 4 bathrooms constructed
  • 1 Ground for open activities cleared.
  • 1 kitchen constructed

f. Project activities 

The project activities shall include the sensitization meetings of ADCs and VDCs, which will see 8, 367 community members, 10 CBO, 10 ADC and 10 VDC members sensitized. Then Identification of a contractor through biding and endorsement by IPC, procurement of construction materials and construction of evacuation centre which comprises of 1 evacuation shelter, 4 pit latrines, 4 bathrooms, and 1 kitchen constructed and 1 activity ground created.

See annex 1.0 for the work plan.

g. Target Beneficiaries

  • The project will be implemented in the area of Traditional Authority Ngabu, Group Village Headman Jombo in Chikwawa district. 
  • The direct beneficiaries are displaced flood victims. It is expected that 8, 367 people are going to directly benefit comprising of 3,912 males and 4, 455 females.
  • The indirect beneficiaries are people within jumbo villages with a combined population of 4200 individuals and 51% of which is made of females. 

h. Project Budget (see annex 2.0)

i. Risk and Assumptions

  • The project will be a failure if the communities will not fulfil their contribution in form of bricks, sand, land and water. However, the chiefs, Village Area Committees and Village Development Committees have already started mobilizing communities to contribute the resources.  
  • We assume that the communities know their problem and that development comes from within the community. This will contribute to the success of the project.

j. Project Sustainability

The project will be managed by Tikumbukireni Community Based Organization with support from Chikwawa District Council. To ensure sustainability of the project, beneficially communities will make a contribution of sand, bricks and provision of water for the construction of the evacuation shelter, pit latrines and bathrooms. The building will also be used to generate income for the CBO through room hiring and renting when it is not occupied by the flood victims. It can be used as a storage facility for some NGOs’ items, wedding functions, for under five clinic and public health issues, village meetings and many more. Some of these activities will bring revenue to the community for maintenances.

k. Consideration of Crosscutting Issues

  • This project will assist in youth development through provision of the ground space. This will help in preventing the youth from bad behavior so that they avoid contracting HIV virus and other infectious diseases. 
  • All the structures under this project will be disability friendly so that the right to access is granted to every member of the community. 

l. Monitoring and Evaluation

The project will be monitored monthly by Chikwawa District Council and quarterly by Department of Disaster Management Affairs (DoDMA). Implementation will be done by Tikumbukireni CBO. The CBO will monitor every activity of project throughout the project life. It is anticipated that the community will be able to maintain the shelter beyond the end of the project

At the end of the project the CBO will welcome the evaluation and auditing of the project and its accounts by the DoDMA.  ANNEX 1.0 

ANNEX1.0 OPERATIONAL BUDGET (FIND ATTACHED BOQ)

 WORK PLAN FOR THE CREATION OF EVACUATION CENTRE  
EXPECTED OUTPUTSPLANNED ACTIVITIESTIMEFRAMERESPONSIBLE PARTY PLANNED BUDGET 
Q1Q2Q3Q4Source of fundsbudget descriptionamount
Output 1.11.1.1 ADC sensitisation meetingsX     TIKUMBUKIRENI CBO  hall hiring  20000
11768 community members and 35 ADC and VDC members sensitized
drinks8,750
snacks8,750
transport refunds70,000
fuel22020
1.1.2 Community and VDC sensitisation meetingX   TIKUMBUKIRENI CB0, VCPChall hiring20000
drinks17,500
snacks17,500
transport refunds1400,000
fuel22,020
Sub total        346,540
Output 2.1         
1 evacuation shelter constructed2.1.1. Identification of a contractor (sourcing of quartations and screening them for endorsement by IPC)X   CBO (IPC)Transports25,000
Meals37000
2.1.2. procurement of construction materialsX   CBO (IPC)Various materials (ref BOQ)9,361,700
transport for the materials650,000
2.1.3 construction of evacuation shelterXXX CBO fee for the contractor2,600,000
Sub total        12,673,700
Output 2.22.2.1 Identification of the contractor X   CBOFee for the contractor160,000
4 toilets constructed2.2.2 Procurement of construction materials  X   CBO (IPC)Transport (from 2.1.2)25,000
Meals  (2.1.1)37,000
2.2.3  Construction of toilets X  CBO (IPC)Various materials (ref. BOQ)873,800
Transport  (from 2.1.3)70,000
Sub total        1,033,800
Output 2.32.3.1 Identification of the contractor X  CBOFee for the contractor100,000
4 bathrooms constructed2.3.2 Procurement of construction materials   X CBO (IPC)Transport (from Admin costs)25,000
Meals (from admin costs)37,000
2.3.3 Construction of bathrooms  X CBO (IPC)Various materials (ref.599,000

Page 6 of 11

        BOQ) 
Transport (from Admin costs)  
Sub total        599,000
Output 3.13.1.1 Creation of playing/parking ground   XTIKUMBUKIRENI CBOCommunityFee for the workers80,000
          
Output 4.14.1.1  Identification of a contractor (sourcing of quotations and screening them for endorsement by IPC)  X TIKUMBUKIRENI CBO (IPC)Transport (from Admin cost)25,000
Meals (from Admin costs)37,000
1 kitchen constructed4.1.2 Procurement of construction materials   X TIKUMBUKIRENI CBO (IPC)Various materials (ref. BOQ)1,415,650
 4.1.3 Construction of the kitchen   XTIKUMBUKIRENI CBO Fees for contractor850,000
        Transport for materials290,000
Subtotal        2,555,650
 Working tools    TIKUMBUKIRENI CBOWheelbarrows172,000
Hoes 16,200
Picks84,000
Brush set5,000
shovels36,000
Water drums81,000
Panga knives 5,000
         399,200
 AdministrationXXXXTIKUMBUKIRENI CBO– Printing and photocopying87,500
Fuel621,000
Transports300,000
Allowances375,000
Bank charges93,600
Photocopy75,000
Airtime120,000
Printing 200,000
Refreshments125,000
Hall hiring 80,000
Maintenance (service)600,000
Sub total      2,677,100
GRAND TOTAL        20,284,990

Page 7 of 11

Project Budget

  BUDGET LINE DESCRIPTION  Total (US$)Total (MK)
Item DescriptionUnitUnit Cost (MK)Quantity
        WORKING TOOLS    Wheelbarrowsnumber43,0004251.95172,000
Hoes number2,700623.7316,200
Picksnumber21,000 4123.0584,000
Brush setNumber5,00017.325,000
shovelsNumber9,000 452.7336,000
Water drumsNumber27,0003118.6581,000
Panga knives Number2,50027.325,000
Sub total    584.76399,200
ADC SENSITISATION MEETING  Hall Hiringnumber20,000129.296  20000
Drinksnumber2503512.828,750
Snacksnumber2503512.828,750
Transport RefundsNumber2,00035102.5470,000
Fuellitre7343032.2622020
Sub total   189.723129,520
COMMUNITY AND VDC SENSITISATION MEETING  Hall HiringNumber20,000129.29620000
DrinksNumber2507025.6317,500
Snacksnumber2507025.6317,500
Transport Refundsnumber200070205.08140,000
Fuellitres7343032.2622,020
Subtotal   317.896217,020
      EVACUATION SHELTER CONSTRUCTIONQuarry stonesTones4,90020143.5598,000
River sandTones4, 50040263.67  180,000
Cement 50 kg bag7,3004204,491.153,066,000
Window panesNumber3209042.1928,800
Brick force wireRolls 2,30050168.45115,000
Bricksnumber1575,0001647.931,125,000
Chrondon litres7,500443.9430,000
Iron sheet (20 feet) – 28gnumber13,500841661.111,134,000
Ridge ironNumber 2,2002270.89748,400
Window framesNumber 21,50010314.94215,000
Door frame Number 23,5003103.2770,500
Rim lockNumber 7,500110.997,500
HarspassNumber 1,800410.557,200
LockNumber 4,400425.7817,600
Ant repellent5L12,50010183.10125,000
Galvanized wirekg1,7004099.6168,000
 Roofing nailskg1,7002049.8034,000
Wire nails (6”)kg1,7001024.9017,000
Wire nails (5”)kg1,7002049.8034,000
Wire nails (4”)kg1,7001024.9017,000
Wire nails (3”)kg1,700512.458,500
Brick siralitres22,500 32.9622,500
Finas10 litre tin20,500130.0320,500
Timber (Fisherboard)Number 7,00013133.29991,000
Timber (6 x 2)Number 5,50040322.26220,000
Timber (4 x 2)number4,5001598.8867,500
Timber (3 x 2)number4,00040234.37160,000
Transport for bricksTrip 250,0001366.21250,000
Transport for cementtrip50,0004292.96200,000
Transport timber and iron sheetstrip50,0001292.96200,000
Doorsnumber35,0003153.81105,000
Construction Contractor number2,600,00013808.542,600,000
Port for window paneskg41012072.0749,200
Varnish5L19,400128.4219,400
One coat lime wash50kg11,35011182.88124,850
Two coats PVA interior paint5L9,90010145.0299,000
One coat full gross5L13,2006116.0179,200
Two coats bituminous on external structure wall5L491503215.99147,450
12mm rod reinforcementeach8,00050585.93400,000
6 mm rod reinforcementeach7,30045480.46328,000
Rubber stoppereach4,100636.0324,600
Hinges of 6 inchesbox14,50012254.88174,000
Wood screwsbox2,00012.932,000
125 Microns(500 gauge polythene damp proof membrane)Rolls30,5006268.06183,000
Ring burglar’s  bar  (Y 12)Number3,50060307.61210,000
 Firewood for burning brickstones90,0005659.17450,000
Sub total18,564.73612,673,700
KITCHEN CONSTRUCTIONIron sheetNumber 6,75030296.63202,500
Cement 50 kg bags7,30070748.52511,000
Roofing nailskg1,700922.4115,300
Roofing wireskg1,7001229.8820,400
6’’ Nailskg1,700614.9410,200
5’’ Nailskg1,7001024.9017,000
3’’ Nailskg1,700614.9410,200
 Fisherboard timberNumber7,00012 123.0584,000
6 x 2 TimberNumber5,50018 145.0299,000
4 X 2 timberNumber 4,50010 65.9245,000
3 X 2 timberNumber 4,00015 87.8960,000
Ring burglar’s number3,50018 92.2863,000
Door frame Number23,5002 68.8547,000
DoorNumber 35,0002 102.5470,000
Ridge Ironnumber2,2007 22.5615,400
Brick force wireRoll 2,30010 33.6923,000
Lime50 kg bag11,3503 49.8834,050
Paint 5 Litre tin13,2003 58.0139,600
Quarrytones4,90010 71.7849,000
Transport for quarry, river sand10 tone trip30,0003 131.8390,000
 Construction contractornumber850,0001 1245.10850,000
 Transport for materialsnumber100,0001 292.96200,000
Subtotal     3743.582,555,650
  TOILET CONSTRUCTION (4.5m x 2.2m)Pit digging (2 m)Number30,000 1×4 175.78120,000
Quarry Tones4,900 1×428.7119,600
Brick force wirerolls2,300 6×476.4652,200
Timber (2 x3) 4.5 m longNumber  3×487.8960,000
Roofing nails kg1,700 1 x 49.966,800
Roofing wirekg1,700 1 x 49.966,800
Cement 50 kg bags7,300 10 x 4427.73292,000
Iron sheetsnumber5400 3 x 494.9264,800
Door framesNumber 23,500 1 x 4137.6994,000
Doors number35,000 1 x 4205.08140,000
Lock  number4,400 1 x 425.7817,600
Construction contractornumber40,000 4234.37160,000
    Sub Total1,514.331,033,800
BATHROOM CONSTRUCTIONTimber (2 x3) 4.5 m longNumber 3×487.8960,000
Roofing nails kg1,7001 x 49.966,800
Roofing wirekg1,7001 x 49.966,800
Cement 50 kg bags7,3004 x 4171.09116,800
Iron sheetsnumber4,8003 x 483.4957,000
Door framesNumber 23,5001 x 4137.6994,000
Doorsnumber35,0001 x 4205.08140,000
Locks number4,4001 x 425.7817,600
Construction Contractornumber25,0001 x 4146.48100, 000
Subtotal   877.43599,000
TIKUMBUKIRENI CBO’s ADMINISTRATIVE COSTSPrinting and photocopyingReam 3,50025128.1787,500
Fuellitres690900909.66621,000
Transports   439.45300,000
AllowancesNumber 2,50015549.31375,000
Bank chargesMonths 7,80012137.1193,600
PhotocopyNumber 1015 X 500109.8675,000
AirtimeCalling cards5,0002 X 12175.78120,000
Printing Number 4 X 500292.96200,000
RefreshmentsNumber 25050 people X 12 sessions 183.10125,000
Hall hiring Number20,0002117.1980,000
Maintenance (service)Number150,0001 x 4 times878.89600,000
Subtotal   3921.472,677,100
GRAND TOTAL (A)  29,713.9320,284,990
            COMMUNITY CONTRIBUTIONGiving land for construction of structures at evacuation centre  Squares meters500,000100732.41       500,000 
Clearing the land for constructionnumber5501000805.65550,000
Collection, packing and offloading of sand into vehicle   Tonnage2,000200585.93          400,000 
Water for molding bricks   Drum   350  3000 drums(100 each)1538.06  1,050,000
Molding bricks  Number  15  50,0001098.62  750,000
Meals during burning of bricks for mean from 18 villagesNumber 502000146.48100,000
Security Guardsnumber15,0002 x 12527.34360,000
Project supervisionmonths150,000122636.681,800,000
  Community Contribution Sub Total (B)8,071.17875,510,000
  Project Grand Total (A+B)37,785.2625,795,090
  Percent Community Contribution21.36

Project One Fundraising Proposal Implementation and Evaluation

Do you find yourself approaching a tight assignment deadline? We have a simple solution for you! Just complete our order form, providing your specific instructions. Rest assured that our team consists of professional writers who excel in their respective fields of study. They utilize extensive databases, top-notch online libraries, and up-to-date periodicals and journals to ensure the delivery of papers of the utmost quality, tailored to your requirements. Trust us when we say that thorough research is conducted for every essay, and our expertise in various topics is unparalleled. Furthermore, we have a diverse team of writers to cover a wide range of disciplines. Be assured that all our papers are created from scratch, guaranteeing originality and uniqueness.

Write my essays. We write papers from scratch and within your selected deadline. Just give clear instructions and your work is done

PLACE YOUR ORDER